Maintenance works funded by Glasgow City Council will be carried out in Ashton Lane and Cresswell Lane in the first two months of 2014.
The work will cover the following:
- Complete re-grout of both Ashton and Cresswell Lanes;
- Lift and relay areas of subsided and rocking setts;
- Extension of setted area to meet the tie in with Byres Road;
- Re-construction (to asphalt) of the damaged granolithic concrete footways at north east end of Ashton Lane (behind Iceland/U Station).
- Lift and relay whin stone kerbs on above footways. Replace length of existing PC Kerbs with reclaimed whin stone kerbs.
- Reconstruction of footway crossing point at entrance to Ashton Lane from Byres Road.
Updated information about the contract works will be available to businesses operating in the lanes.
This investment in the historic back lanes of the Hillhead area is very much welcomed. It will improve the general access for pedestrians and restore the appearance of these distinctive areas for visitors and residents alike.